INSTALLATION
EATON Powerware
®
9125 (9910-E30) UPS Installation Guide for IBM
®
Applications S 164201696 Rev 1
10
11. Slide the UPS and any optional cabinets into the rack.
12. Secure the front of the cabinets to the rack using two pan-head
screws on each side (see Figure 10).
Position 6
Position 1
Figure 10. Securing the Front of the Cabinet
13. Loosen the wing nut on each rear hold-down bracket and slide the
bracket over the rear of the cabinet. Tighten the wing nut.
Rear Hold-Down
Bracket
Figure 11. Securing the Back of the Cabinet
14. Tighten the pan-head screws that secure both rails to the front of
therack(seeStep3onpage6).
15. Continue to “EBM Installation” on page 15, “PDM Installation” on
page 17, or “Power Connections and Startup” on page 20.