INSTALLATION
EATON Powerware
®
9125 (9910-E30) UPS Installation Guide for IBM
®
Applications S 164201696 Rev 1
5
4. Reinstall the UPS front cover (see Figure 3).
Figure 3. Reinstalling the Front Cover
Setup and Installation
The E30 UPS is designed for flexible configurations and can be installed
in a r ack, as a standalone cabinet, or in a tower configuration.
NOTE For UPS rack installations: If the UPS is pre-installed in an IBM rack, continue
to “UPS Installation” on page 18. If you are installing the UPS in an IBM iSeries (0550, 0551,
0554, or 0555 types) or pSeries (7014 type) rack, continue to the following section, “Tools
Required.” If you have another type of rack, contact your service representative (see page 49).
NOTE
For UPS standalone cabinet or tower installations: Continue to “Tower
Setup” on page 11 to begin the UPS setup.
Tools Required
To assemble the components, the following tools may be needed:
S Medium flat-bladed screwdriver
S #2 Phillips screwdriver
S 7and8mmwrenchorsocket
Rack-Mount Setup
The rail kit can be installed in 48-cm (19-inch) racks and needs only 2U of
valuable rack space.
NOTE Mounting rails are required for each individual cabinet and are located in the UPS
and EBM cartons. All hardware is supplied.
NOTE The UPS and any optional cabinets MUST be installed at the bottom of the rack. If
placed in a rack with existing equipment, the rack must be reconfigured to allow the UPS
installation at the bottom of the rack.