INSTALLATION
EATON Powerware
®
9125 (9910-E30) UPS Installation Guide for IBM
®
Applications S 164201696 Rev 1
15
EBM Installation
CAUTION
A small amount of arcing may occur when connecting an EBM to the UPS. This is normal and
will not harm personnel. Insert the EBM cable into the UPS battery connector quickly and
firmly.
To install the optional E BM(s):
1. The UPS has a battery connector cover that must be removed
before installing t he EBM(s). Remove the cover from the rear panel
as shown in Figure 21.
NOTE Keep the battery connector cover and screws for future use. If the UPS is stored or
used without an EBM, the battery connector cover must be installed as a safety precaution.
Battery Connector Cover Screws
Figure 21. Battery Connector Cover
2. Remove the cover from the EBM cable as shown in Figure 22.
NOTE Keep the EBM cable cover and screws for future use. If the EBM is stored or
removed from the UPS, the EBM cable cover must be installed as a safety precaution.
EBM Cable with Cover
Figure 22. EBM Cable Cover