XS series operating manual 
 
XS user manual v0.55  - 86 - 
Multiple ground continuity operation  
 
With the above example, after starting the test the LCD screen shows : 
 
 
Fig 10.13 
 
The unit waits that the operator press on the ENTER key (or press on the remote control bush button 
on the test probe if featured) to start the ground continuity test step (STEP:1) 
Then the first step is proceeding.  
The first line displays the measurement result. 
And the LCD screen shows: 
 
 
Fig 10.14 
 
As previously the unit goes in standby, waiting for ENTER pressing. 
 
This is done as many times as the number of test steps if the test results are PASS. 
Otherwise, the unit offers to the operator the possibility to re-test the FAIL test or to stop the 
Sequence (press on ESC).