Expert SmartTurn - Re-commissioning in the plant

Expert SmartTurn
70 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Turntable control SmartTurn
Installation and commissioning
52 Dok-ID:EXPERT-0003-EN-2011
5.4.1 Re-commissioning in the plant
When re-commissioning the turntable in the plant the settings
made during the commissioning process must be checked and any
adaptations to local conditions must be executed.
Re-commissioning sequence
1. Switch on the operating voltage.
2. Turn the turntable several times at creep speed.
3. Check direction of motor rotation, drive roller.
4. If necessary change direction of motor rotation and set
clockwise / counter-clockwise drive roller direction.
5. Press the reset button 3s - system fault LED goes out
6. Turn the turntable several times at operating speed.
If the turntable stops several times without fault in the 0-position,
the self-adjustment and re-commissioning are concluded.
NOTE!
After first-time operation of the turntable with the
customer load, or after changes to the load,
overrun faults could occur. In this case it is
necessary to turn the turntable several times at
operating speed until the turntable controller has
concluded the optimization process.