Commissioning HyPower-Geko
94 FläktGroup DC-2014-0022-GB 2018-05/R5 • Subject to modifications
7.1.2 The following pre-commissioning checks must be performed:
• Check that the HyPower-Geko
(ceiling mounting) is properly secured.
• Manually check the mounting of actuators (fig. 7-1, pos. 1 sample).
• Tighten all screw connections on medium connections
(fig. 7-1, pos. 2).
• Check all electric connections according to the available wiring diagrams and check
all terminal connections for secure seating.
• Proceed with commissioning (see Chapter 7.2).
• Check all built-in components for soiling and clean if necessary.
Pos. 1: Actuators
Pos. 2: Screw connections medium connection
Fig. 7-1: Pre-commissioning checks: