EasyManua.ls Logo

Froling S3 Turbo - 2.2 Pictograms used

Froling S3 Turbo
73 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
1.3 Requirements at the place of installation
1.3.1 Approval for the heating system
The appropriate supervisory authority (inspection agency) must always be informed
when installing or modifying a heating system, and authorization must be obtained
from the building authorities. Also observe ANSI/NFPA 211 and CAN/CSA B365 for
the installation.
1.3.2 Space required
FOR SAFE INSTALLATION AND OPERATION CLEARANCES TO COMBUSTIBLES
MUST BE MAINTAINED.
The diagram below shows how much space is required for the system in the boiler
room.
The boiler may only be installed on non-combustible floors with these clearances.
Dimens
ion
Name S3 Turbo
A Distance - front of boiler to wall 36“ (900 mm)
B Distance – side of boiler to wall 32“ (800 mm)
C Distance – back to wall 14“ (350 mm)
D Distance – side of boiler to wall 9“ (250 mm)
Distance between ceiling and boiler 18“ (460 mm)
1
Safety
Requirements at the place of installation
8 Froling GesmbH | A-4710 Grieskirchen | www.froeling.com

Table of Contents

Other manuals for Froling S3 Turbo

Related product manuals