GE Power Management
735/737 Feeder Protection Relay 6-5
6 TESTING 6.2 TEST RECORDS
6
6.2.5 INSTANTANEOUS PHASE OVERCURRENT PICKUP TEST
6.2.6 INSTANTANEOUS GROUND OVERCURRENT PICKUP TEST
6.2.7 INSTANTANEOUS PHASE OVERCURRENT TIMING TEST
6.2.8 INSTANTANEOUS GROUND FAULT OVERCURRENT TIMING TEST
PHASE AND LEVEL DIAL SETTING
(xCT)
INPUT CURRENT
()
STATUS
PHASE 1 / LOW END
PHASE 1 / HIGH END
PHASE 2 / LOW END
PHASE 2 /HIGH END
PHASE 3 / LOW END
PHASE 3 / HIGH END
PHASE AND LEVEL DIAL SETTING
(xCT)
INPUT CURRENT
()
STATUS
GROUND / LOW END
GROUND / HIGH END
PHASE AND LEVEL DIAL SETTING
(xCT)
INPUT
CURRENT ( )
EXPECTED
TIME (ms)
MEASURED
TIME (ms)
STATUS
PHASE 1 / LOW END ≤ 35
PHASE 1 / HIGH END ≤ 35
PHASE 2 / LOW END ≤ 35
PHASE 2 /HIGH END ≤ 35
PHASE 3 / LOW END ≤ 35
PHASE 3 / HIGH END ≤ 35
GROUND LEVEL DIAL SETTING
(xCT)
INPUT
CURRENT ( )
EXPECTED
TIME (ms)
MEASURED
TIME (ms)
STATUS
GROUND / LOW END ≤ 35
GROUND / HIGH END ≤ 35