Set-up 5
0020237648_03 Installation manual 27
A Cold roof B Warm roof
1. Determine the installation site for the roof duct.
2. Insert the flat roof penetration collar (2).
3. Glue the flat roof penetration collar in place.
4. Insert the roof duct (1) through the flat roof penetration
collar from above and push it down until it is flush.
5. Align the roof duct vertically.
6. Secure the roof duct to the roof construction using the
fixing bracket (3).
7. Connect the roof duct to the product using extensions,
elbows and, if required, a partition.
8.
Alternatives 1:
Condition: Roof duct with extension
▶ Install the extensions. (→ Page 28)
▶ Install the sliding sleeve. (→ Page 28)
▶ Connect all of the pipe joints with air pipe clamps.
(→ Page 37)
8.
Alternatives 2:
Condition: Roof duct without extension
▶ Install the sliding sleeve. (→ Page 28)
5.2.3.4 Installing the pitched-roof duct
1. Determine the installation site of the roof duct in such a
way that there is sufficient distance behind the product
in order to connect the product to the heating installa-
tion.
2. Insert the pitched roof tile(2).
3. Insert the roof duct (1) through the pitched roof tile from
above and push it down until it is seated firmly.
4. Align the roof duct vertically.
5. Secure the roof duct to the roof construction using the
fixing bracket (3).
6. Connect the roof duct to the product using extensions,
elbows and, if required, a sliding sleeve.
7.
Alternatives 1:
Condition: Roof duct with extension
▶ Install the extensions. (→ Page 28)
▶ Install the sliding sleeve. (→ Page 28)
▶ Connect all of the pipe joints with air pipe clamps.
(→ Page 37)
7.
Alternatives 2:
Condition: Roof duct without extension
▶ Install the sliding sleeve. (→ Page 28)
5.2.3.5 Connecting the roof duct
1 Roof duct
2 Extension
3 Sliding sleeve
4 Locking screws
1. Install the extensions. (→ Page 28)
2. Install the sliding sleeve. (→ Page 28)
3. Connect all of the pipe joints with air pipe clamps.
(→ Page 37)