4. Assembly and Installation
PNEG-1156ETL Design III Series Grain Stir-Ator CSA 27
Trolley
NOTE: 36' and larger double auger trolleys require the hold-down rods to be moved to the bottom hole
position. This is done by removing the spring clip and pulling the rod out and reinserting it in the
bottom holes from the side away from the down auger motors. Make sure holes are aligned.
(See Figure 4N for proper location the hold-downs.)
Figure 4N
1. Place trolley on the frame with the junction box toward the center of the bin. Double and triple auger
trolleys are placed on the frame rails from the inboard end. (See Figure 4O.)
Figure 4O
NOTE: Slide trolley in before the inboard. Make sure down auger motors are on the opposite side of
the gear motor.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GSi DMC Design III Series and is the answer not in the manual?

GSi DMC Design III Series Specifications

General IconGeneral
BrandGSi
ModelDMC Design III Series
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals