4. Assembly and Installation
44 PNEG-1156ETL Design III Series Grain Stir-Ator CSA
Check Movement
Move trolley from the extreme outboard end of the main frame to the inboard end and back again to be
sure there is no trolley interference and that there is sufficient electric cord allowed from the support swing
arm to reach both ends.
Power
A professional electrician must be employed to bring the power line to the Stir-Ator. The bin must be
grounded and all the wiring must be done in accordance with local and national codes to avoid bodily injury
and even death.
Installing Stir-Ator Augers
Determine the Required Length of the Auger
Install Stir-Ator augers by standing them up against the trolley to measure length. When measuring the
auger length, be sure the trolley is close to the bin wall. If the unit has been correctly installed the
measurement between the drying floor and the Stir-Ator will be the shortest at the wall.
The Stir-Ator augers should clear the drying floor by 3" for bins up to 30' and 4" for bins 33' and over.
If a grain flow system or bin sweep is installed or to be installed, refer to the owner’s manual for those
products or contact your dealer or The GSI Group for auger floor clearance specifications.
(See Figure 4AU
on Page 45.)