INSTALLATION
June 1999
96-8000
ANCHORING I NSTRUCTIONS
Anchors must be installed prior to setting the machine in place.
IMPORTANT! READ THE INSTRUCTIONS THOROUGHLY BEFORE ATTEMPTING TO ANCHOR THE MACHINE.
ANCHORING KIT: (P/N# 30-0088) QTY
5/8-11 x 6 hex head bolt 6
5/8-11 x 2 1/8 coupling nut 6
5/8-11 x 8 stud 6
5/8 washer 6
5/8-11 hex nut 6
3/4-10 x 6 hex head bolt (FULLY THREADED)6
3/4 10 hex nut 6
anchor strap 6
floor plate 6
epoxy (chock fast gray, PR-610 FR) 11 lbs
Note: There is only enough epoxy to fill the 1.5îš” Dia. x 8.5îš” deep holes.
REQUIRED TOOLS:
Carpenterîš’s square
Hand drill and mixer blade
The anchoring kit contains enough supplies to build six complete anchors. Small vertical
mills only require four anchors. Refer to the anchor patern for the specific machine re-
quirements.
Before drilling the anchor cores, make sure there is enough clearance around the machine
to install the coolant tank. Refer to the appropriate page for machine footprint and coolant
tank dimensions.
Note: To avoid breakage in the concrete ensure that bored holes are at least 12
inches away from any concrete joints.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Haas VF-1 and is the answer not in the manual?

Haas VF-1 Specifications

General IconGeneral
BrandHaas
ModelVF-1
CategoryPower Tool
LanguageEnglish

Related product manuals