6.3. RPE – CONTINUITY MEASUREMENT ON PV MODULES/STRINGS/FIELDS
The purpose of this measurement is performing a continuity test of the protective and
equipotential conductors (e.g.: from rod to earth and connected foreign earth) and earth
rods of SPDs on PV installations. The test must be carried out using a test current >
200mA in compliance with standards IEC/EN62446-1 and IEC/EN61557-4.
CAUTION
We recommend a preliminary check of correct functioning of the instrument
before carrying out a measurement by shorting input terminals E and C,
checking an almost zero continuity value and an out-of-scale value with
terminals E and C open
6.3.1. Calibration of measuring cables
1. Position the cursor onto RPE by using the arrow keys
(,) and confirm with ENTER. The display shows the
following screen:
RPE 15/10 – 18:04
R - - -
Itest - - - mA
STD 2.00 - - -
MODE Lim.
><
2. Use the arrow keys or and select the position “><”.
The display shows the screen to the side.
RPE 15/10 – 18:04
R - - -
Itest - - - mA
STD 2.00 - - -
MODE Lim.
><
3. Connect the measuring cables to each other as shown in Fig. 5.
Fig. 5: Compensation of the measuring cables resistance