4.2 (Optional) Installing a Intelligent Power
Distribution Unit
Procedure
Step 1 Install the DCDB48-200-16B intelligent power distribution unit in the 19-inch rack.
Figure 4-2 Installing the DCDB48-200-16B intelligent power distribution unit
Step 2 Installing a ground cable for the DCDB48-200-16B intelligent power distribution
unit.
Figure 4-3 Installing a ground cable for the DCDB48-200-16B intelligent power
distribution unit
(1) Cabinet or site ground bar
----End