INTERNAL
ESCUTCHEON
EXTERNAL
ESCUTCHEON
APPLY RING OF CAULKING
TO BACKSIDE OF
ESCUTCHEON
FOR BOTH INTERIOR AND
EXTERIOR ESCUTCHEON
PROCEDURE:
1. CUT HOLE ½" LARGER THAN
PIPE O.D. WITH HOLE SAW
2. FILL GAP WITH FOAM
3. APPLY ESCUTCHEON AS SHOWN
4. USE POLYURETHANE CAULK
CAULK EDGE A
MATTE SIDE
GLOSSY SIDE
CLEAN AREA WHERE ESCUTCHEON WILL BE
APPLIED WITH ALCOHOL & CLEAN RAG
COIL
CONNECTION
Caulking Gray 013-03317-050
Champagne 013-03317-040
Champagne Touch-up
Spray Paint
044-03504-000
WATER & STEAM COILS
NOMINAL ESCUTCHEON
PIPE DIMENSIONS
SIZE O.D. I.D.
0.50 3.0 0.550
0.75 3.0 0.815
1.00 3.0 0.815
1.50 6.0 1.400
2.00 6.0 1.875
2.50 6.0 2.375
3.00 6.0 3.000
4.00 7.0 4.000
DX/REFRIGERANT COILS
ESCUTCHEON
CONNECTION DIMENSIONS
SIZE O.D. I.D.
0.500 3.0 0.175
0.625 3.0 0.550
0.875 3.0 0.550
1.125 3.0 0.815
1.375 3.0 1.000
1.625 6.0 1.315
2.125 6.0 1.875
2.625 6.0 2.375
3.125 6.0 2.875
ESCUTCHEON
JCI PART NO. O.D. I.D. THICKNESS
028 14910 001 3.0 0.175 0.125
028 14910 002 3.0 0.550 0.125
028 14910 003 3.0 0.815 0.125
028 14910 004 3.0 1.000 0.125
028 14910 005 6.0 1.315 0.125
028 14910 006 6.0 — 0.125
028 14910 007 6.0 1.400 0.125
028 14910 008 6.0 1.875 0.125
028 14910 009 6.0 2.375 0.125
028 14910 010 6.0 2.875 0.125
028 14910 011 6.0 3.000 0.125
028 14910 012 7.0 4.000 0.125
9. All modied panels must provide integrity equal to original
equipment specications.
10. Reconnect any components, bulkheads or other xtures
that were disconnected from panel in step # 1.
11. Thoroughly clean up inside and outside air unit.