PTX1000 Site Preparation Checklist
The checklist in Table 17 on page 50 summarizes the tasks you need to perform when preparing a site for
a PTX1000 installation.
Table 17: Site Preparation Checklist
DatePerformed byFor More InformationItem or Task
Environment
“PTX1000 Environmental Requirements and
Specifications” on page 52
Verify that environmental
factors such as temperature
and humidity do not exceed
router tolerances.
Power
Measure the distance
between external power
sources and the router
installation site.
•
PTX1000 AC Power Specifications on page 44
•
PTX1000 DC Power Specifications on page 46
Calculate the power
consumption and
requirements.
Rack
“PTX1000 Rack Requirements” on page 56Verify that your rack meets
the minimum requirements
for the installation of the
router.
“PTX1000 Clearance Requirements for Airflow
and Hardware Maintenance” on page 54
Plan rack location, including
required space clearances.
Secure the rack to the floor
and building structure.
Cables
50