InstallationandOperationManual
36

SystemCheckout
Thefollowingaretherecommendedstepsthatshouldbefollowedbeforeandduringthepoweringupofthe
FW106/FW106C.
BeforeTurningthePowerON
1.Topreventsparking,DONOTconnectthebatteryfirst.Connectingthebatteriesshouldonlybedoneoncethe
systemhasbeenpoweredfromthemainACSupply.
2.Checkallfield(external)wiringforopens,shorts,andground.
3.Checkthatallinterconnectioncablesaresecureandthatall connectors
arepluggedinproperly.
4.Checkallswitchesforpropersetting.
5.ChecktheACpowerwiringforproperconnection.Observe/checkslideswitchposition.
6.ClosethefrontcoverplatebeforepoweringthesystemfrommainACsupply.
PowerupProcedure
1.AftercompletingBeforeTurningthePowerONprocedures,powerupthepanel.
ThegreenACONLEDshouldilluminate.
2.Sincethebatteriesarenotconnected ,theBatteryTroubleLEDshouldilluminate,the
TroubleLEDshouldflashandtheTroubleRelay(onthemainboard)willbeactive.
3.Connect
thebatterieswhileobservingcorrectpolarity;theredwireispositive(+)andblackwireisnegative
().
4.AllindicatorsshouldextinguishexceptfornormalpowerACONgreenLED.
