Installation
6. Test each air cannon by firing it five times. Wait after every
discharge until the air cannon tank is completely filled and the
filling process is completed. This can be determined by loud
rustling noise in the tank or by the gauge display (if provided).
NOTE
A signal is sent to the electro-solenoid valve when the installation
is correct and the selected air cannon is fired.
NOTE
The air cannon can be started up if correctly functioning. Refer to
Section 7 “Troubleshooting” if problems occur.
NOTE
Make certain that the air cannon is always filled with compressed
air or protected by a safety slide. This makes it ready to operate at
all times and no process material can penetrate it.