Operation Manual Menzi Muck A91 Page 39
Transport, packaging and storage
The procedure for unloading is the reverse of that of loading.
7. Swivel the upper structure by 180°
(pull up boom and dipper when
swivelling).
8. Position the excavator arm bet-
ween the front support and then
place on the ground
9. Lower the boom and at the same
time slightly extend the dipper
so that the complete excavator is
lifted to the height of the loading
bridge.
10. Extend the excavator arm inclu-
ding the telescope and at the
same time activate the travelling
gear until the machine is comple-
tely on the loading bridge.
11. Before the excavator arm is lifted,
make sure that the steering wheels
are fully on the loading bridge.
12. Move the machine to the required
position using the hub engine.
13. Lower the excavator arm onto the
loading area.
14. Switch off the motor.
15. Release the residual pressure
from the hydraulic system.