2. Installation criteria – Principles
2.1 Site survey – Design criteria
A site survey is the first project input, and it is
of great importance that this is performed and
archived in a proper way. We recommend that all
points in our Site Survey template are considered,
and that existing on-site conditions are docu-
mented preferably with photos and drawings.
Depending of the size of a ceiling lift installation
project, it is also of importance to consider how to
organize logistics for a ceiling lift installation:
When should the installation take place (in
larger building projects)?
What floor is the installation to be done?
How do we get the rails there? (Crane?
Elevator? Stairs?)
How to install efficiently? Installations teams or
single workers?
How to handle disposals (packaging materials)?
2.2 Lifting points
One important issue in the survey is to identify
and define lifting points and optimal placement of
the rail systems.
Figure: Furniture and lifitng points
100 cm