2.3 Mounting Molift Rail System
The way of mounting a ceiling lift system is based
on the specific materials and structural design on
each specific site.
Ceiling materials:
- Concrete; hollow core slabs or compact
layers
- Wood structures (requires reinforcements
between rafters)
- Light materials (LECA, Siporex etc)
Wall materials:
- Concrete
- Bricks
- Wood structure
- Light walls (Gyproc/plasterboards)
Upright supports:
- Upright supports are used where the exist-
ing structure or other installations does not
allow fixing in walls or ceiling.
Reinforcements to existing structues
- Reinforcements must be installed if the
existing building structure OR the materials
are too weak for the installation
Figure: Example of reinforcement of wood wall
structure with upright reinforcement between two
studs for mounting of wall bracket or wall rail.
Figure: Example of reinforcement of wood ceiling
structure with joist hangers and reinforcement
between joists.
Figure: Example of reinforcement of wood ceiling
structure with lying joist over joists.