Installation RMC / RZ / RM / RL
18 © robatherm
Seal sections of max. 100 mm, for this:
Apply solvent welding material (5) with a flat brush (2) in direction of laying directly in
front of the roofing strip (1) approx 5 to 10 cm on the roof to the right and left of the
division area.
Immediately press on the roofing strip with the flat of your hand and place heavy
weight (e.g. sand bag) on adhesion points.
Repeat work process. The weight need not be left on the adhesion points for a long
time.
Seal the abutment edges (7) of the roofing strip with the PVC solution, for this:
Squeeze the plastic bottle and press the PVC solution continuously into the edge as a
thin strand. The solution quickly dries into a compact film.
Close transport lug openings as described.
Note
If it rains during unit assembly the roof must be covered with a tarpaulin for example.