1.3
Start up and commissioning of the xentra should be performed in the order presented
in this manual:-
Installation (section 2)
This section takes commissioning to the point where the xentra is powered and
operational. The installer is advised to read this section completely before commencing
installation.
Initial configuration (section 3)
This section serves as a tutorial for the user interface and ensures that the password
and clock are set before calibration. Setting the clock ensures that calibration activity
is correctly recorded in the calibration history file.
Calibration (section 4)
This section describes manual calibration, automatic calibration, manual calibration
check and automatic calibration check.
Main configuration (section 5)
This section describes setting up of alarm levels, analogue outputs, relays and other
parameters.
Review (section 6)
This section describes how to display analogue output settings, relay allocation, alarms,
faults and analyser identity without changing the analyser settings.