Building Technologies
10 Installation checklist
The following list serves as a checklist or task list for the installation personnel. It
includes all components available as options. It can be copied and handed out to
the installation personnel with the installation instructions.
Position Type Component/task Notes Complete
1 Install rear panel
2 Install housing extensions
Additional empty housing for further
components (e.g. batteries)
3 Connect mains cable
Note country-specific terminal
allocation
4 Install operating unit Standard
5 Install operating add-on
In bottom half of housing or in
additional housing
6 Install cover
7
Install periphery board Only after a disassembly
8 Install fire terminal board Only after a disassembly
9 FP2015-A1
Install a power supply
(70 W)
Option for fire terminal
10 FP2004-A1
Install a power supply
(150 W)
11
Install shield connection
terminal blocks
Included in country kit [DE] FA2001
12 FCI2003-A1
Installing loop extension
(C-NET)
Max. 2 modules depending on the
periphery board
13 Z3B171 Install relay module
14 FHA2007-A1 Install mounting plate Mounting above the periphery board
15 FCI2001-D1
Install fire brigade
periphery module [DE]
Only for Germany.
Note different mounting possibilities
16 FN2001-A1
Install network module
(SAFEDLINK)
Max. 2 modules
Ensure correct installation site
17 FCA2006-A1
Connection module (card
cage)
Only if replaced (FC723 and FC726)
18 FCA2007-A1
FCA2008-A1
Card cage (2 slots)
Card cage (5 slots)
Only if replaced (FC723)