7.3 Commissioning procedure
The chapter describes the commissioning of the motor
Precondition
You have mounted and connected the motor correctly.
All safety relays are functional and activated.
Ensure that the frequency converter is correctly parameterized.
You are connected to the converter, e.g. via the Pro󹪝net interface X127.
You have an Internet connection.
Procedure
Note
Incorrect 󹪝rst commissioning due to power interruptions
Software updates are loaded when commissioning the motor at the converter for the 󹪝rst time.
These updates can take some time. The system does not respond in this time.
The drive will not be correctly commissioned if you interrupt the system power supply in this
phase.
During the complete commissioning phase, ensure that the power supply is never
interrupted.
1. Start the commissioning tool in the converter, e.g. STARTER, STARTDRIVE or the Web server
2. Follow the steps of the commissioning tool to commission the motor
You have commissioned the motor.
Switching o󹪜
Switch o󹪜 the motor at the frequency converter.
Commissioning
7.3 Commissioning procedure
SIMOTICS S-1FK2 synchronous motors for SINAMICS S120
86 Operating Instructions, 02/2022, A5E46089564B AD

Table of Contents

Other manuals for Siemens SIMOTICS S-1FK2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMOTICS S-1FK2 and is the answer not in the manual?

Siemens SIMOTICS S-1FK2 Specifications

General IconGeneral
BrandSiemens
ModelSIMOTICS S-1FK2
CategoryEngine
LanguageEnglish

Related product manuals