Connecting External Sources SMA Solar Technology AG
112 SI5048-TEN093630 Technical Description
Generator Interface "234.07 GnSrtMod" = Autostart; Generator Request by
Sunny Island
Generator Interface "234.07 GnSrtMod" = GenMan; Generator Request Via
Sunny Island
1 Generator started by Sunny Island
2 Generator Start
3 Beginning of warm up time
4 Warm up time has expired
5 Generator is connected
6 Current limit
7 Minimum running time expired
8 Current is reduced, battery absorption phase
9 Charging process is completed, generator disconnection
10 Generator power down time expired, generator disconnection
11 Stop time has expired
1 Generator start by Sunny Island using GenMan
2 Generator start by GenMan
3 Beginning of GenMan warm up time
4 GenMan warm up time has expired, connection signaled by
GenMan at Sunny Island
5 Sunny Island connects generator
6 Current limit
7 Minimum run time (Sunny Island) has expired
8 Current is reduced, battery absorption phase
9 Charge process complete, generator disconnected by
Sunny Island
10 Signal at GenMan
11 GenMan power-down time has expired, generator stopped
12 Stop time has expired
Power-Dependent Generator Start
Warm up times, minimum run times and power down times are also maintained for power
dependent generator starts.