Preparation before Installation
-20°C-+53°C
No direct sunlight No rain exposure No snow lay up
Rain exposureNear combustibles Direct sunlight Snow lay up Near antenna
IP6
5
5-95%RH
4.1.2 Installation Carrier Requirement
The mounting location must be suitable for the weight and dimensions of the product and
the support surface for installation must be made of a non-flammable material.
Solid brick/concrete;
Either floor mounting or wall mounting, the bearing capacity of the area to place
or install a battery module must be over 200 kg;
Please ensure that the thickness of any part of the wall should not be less than
100 mm;
The device must not be installed on the wood wall.