6 Using the product
61
Parameter Explanation
Test pressure (target) Set test pressure
The ZVSHK sheet as per DIN EN
806-4 stipulates the following
times and pressures:
Testing crimp connections:
pressure max. 6 bar, test time
15 min
Testing metal multi-layer
composite and PVC pipes:
pressure max. 11 bar, test
time 30 min
Testing PP, PE, PE-X and PB
pipes and combined
installations made of metal
and multi-layer composite
pipes:
Pressure 11 bar, test time
30 min
Reduce pressure to
5.5 bar (drain water from
system), further test time
of 120 minutes.
1. Edit values: [Edit].
2. Enter values. [], [] and sometimes [], [] [OK].
Carrying out a test
To prevent the penetration of moisture into the instrument,
dry hoses should be used.
- The test pressure (target) must be built up manually.
1. Start measurement: [].
- Zeroing starts (5 s)
Option
> End stability time early: [Next]
> End measurement period early: [Next]
- Measurement is cancelled.
- Testing of crimp connection ended: [Next].
2. Start pressure test: [Next]
- Zeroing starts (5 s)