USER'S GUIDE____________________________________________________________________  
98 __________________________________________________________________ M210855EN-D 
Testing the Operation of Relays 
If a relay module is installed on PTB330, you can use either the 
optional display and menus or the serial line command 
RTEST to test 
the operation of relays. For testing via menus see section Testing the 
Operation of Relays on page 61. 
Testing activates r
elay
s even if they are disabled. 
Use the module push buttons to activate the relays. Press the REL 1 or 
REL 2 button to activate the corresponding relay. 
Relay is activated:    led is lit 
Relay is not activated:    led is not lit 
 
RTEST 
Use the serial line command RTEST to test the operation of the 
relays. 
RTEST [x1 x2] 
where: 
x = ON/OFF 
 
Example: use the command to activate and then release the relays. 
>rtest on on 
ON ON 
>rtest off off 
OFF OFF 
> 
 
Enter the command RTEST without parameters to stop testing.