Vertiv | Liebert CRV+ | User Manual 12
Chapter 2 Installation
The Installation process consists of the following procedures, namely-
Pre-installation
Installation Preparation
Mechanical Installation
Electrical Installation
2.1 Pre-installation
Pre-installation contains the following 3 sub sections, namely-
Transportation & Movement
Unpacking
Inspection
2.1.1 Transportation & Movement
When it comes to transporting the system, Railroad is the most preferable choice. However, if railroad
transportation is not possible, then the truck transport option is an optimal choice. One precaution is to
choose roads that do not have too many bumps and if any, avoid it as much as possible.
Liebert CRV+ systems are on the heavier side and therefore, it is recommended that equipment
like an electric forklift is utilized for these heavy duty systems.
Move the equipment to a location which is in the vicinity of the installation site.
If an electric forklift is used, insert the tines of the forklift below the pallet as displayed in
Figure 2-1. Align the tines with the center of gravity to prevent the equipment from falling over.
Figure 2-1 depicts the way the tines of the forklift are inserted below the pallet and in the same
image, the graphic to the right indicates that the tines are aligned with the center of gravity to
prevent the equipment from falling over:
Figure 2-1 Moving the equipment using a Forklift truck