26 Cascadeoperation-Fluegas
headerdesign
For open ue operation, there must be an aperture in the boiler room that opens to the
outside and has a clear cross-section of at least 150 cm².
Where necessary, adapt the installation examples to the relevant building regulations
and requirements in your country/region. Discuss any questions relating to the
installation, particularly of inspectioncoversandventilationapertures(ventilation
generallyrequiredabove50kWoutput)with your local heating engineer.
Fluegasroutingwithheader
Oil condensing boilers with common ue routing - open ue operation in installation
type B23.
The effective heights specied are only valid on the condition that the length of the ue between the individual appliances and
downstream of the last appliance does not exceed 2 m. 325 m was assumed as the geodetic height. If the conditions at the
installation site are different, an individual calculation is required.
Number
2x
COB-29
2x
COB-29
3x
COB-29
4x
COB-29
2x
COB-40
3x
COB-40
4x
COB-40
Installation Type B23
Flue internal diameter DN 110 DN160 DN160 DN160 DN160 DN160 DN160
Total ue gas mass ow rate g/s 26,6 26,6 40.0 53,3 35,0 52,5 70,0
max. Flue gas temperature °C 76 83
Max. effective building height m 30
Cascade control with header
DWTK
min. 600
max. 1000
KM module
Flue cascades are only suitable in balanced ue operation. They must be designed to
EN 13984-1.
Topreventuegasescaping,auecascadeisonlypermittedwitha
testeduegasdamper.Escapingwastegasmayleadtoasphyxiation
orseveretolife-threateningpoisoning.
Fluecascade
Ceiling height at least 2500 mm