Completingtheadjustments
- Check the control parameters and match them to the system if necessary.
- Check the condensate drain.
- Instruct the customer in the operation of the device, with the aid of the operating and
installation instructions.
- Complete the commissioning report(see the commissioning report chapter) and
hand over the instructions to the customer.
- Instruct the customer about the need for annual servicing.
- Instruct the customer about energy saving options.
- Refer your customer to section "Information regarding energy efcient operation" in
the operating instructions.
- After completing the work, ret the casing cover and check the CO
2
value with the
boiler closed.
- When correctly set, the boiler should not exceed the maximum CO
2
values in
accordance with the table below.
Applianceclosed COB-15 COB-20 COB-29 COB-40
CO
2
max
Stage 2 13,5 %
Stage 1 13,5 %
O
2
min.
Stage 2 2,7 %
Stage 1 2,7 %
- If the CO
2
value increases too greatly, the balanced ue must be checked.
- Enter ue gas values such as CO
2
content, ue gas CO content and soot value in the
commissioning report (see the commissioning report chapter).
- Terminate the emissions test mode by turning the program selector switch on the
BM programming module to the required operating mode. If emissions test mode
is not reset manually, the appliance switches back to the original operating mode
automatically after 15 minutes.
- Remove the test probe and close the test port.
Ensure the cap is seated rmly.
C)CheckingtheCO
2
adjustment
31 CO
2
check/adjustmentbymatching