4.5 Commissioning
Commissioning follows installation and power-up of the detector and involves the following steps:
1. Use Xtralis VSC to:
l Accept factory default configurations.
l Check that the fire-alarm threshold setting is appropriate to the pre-engineered design used.
l Select appropriate air flow threshold setting.
l Normalize the air flow.
2. Functionally test the detector by introducing smoke into the last hole.
3. Record and confirm the transport time is less than 90 seconds.