Hardware Installation
4.2.7 Installing the Cabinet with Earthquake Bracing
Table 8 Earthquake Set, Concrete Floor
17/BYB 501/1 (2 x SXK 118 0168/1) Earthquake Set, Concrete Floor
Pos. Title/Function Product Number Quantity
A FIXING IRON SXA 123 0380/1
4
B BAR SXA 123 0381/1
2
C COASTER SXA 123 0382/1
4
D EXPANDER SCREW M 12/25 NSV 907 02
4
E INSULATING BUSHING SXA 106 0093/2
4
F WASHER SCA 118 210/78
4
G WASHER SCA 118 170/78
4
H SCREW M 16X25 03/SBA 186
160/0250
4
Figure 19 Installing the Earthquake Bracing
Note: The following procedure must be performed for the feet at the front
and for the feet at the back:
Slide the earthquake bracing under the cabinet between the feet, Figure 19
on page 33
Verify that two coasters (C) are installed under the two fixing irons (A).
33
6/1531-ASP 113 01 Uen J2 2008-07-17