Hardware Installation
Figure 21 Securing the Earthquake Bracing
Note: The following procedure must be performed for the feet at the front
and for the feet at the back:
• Place two expander screws (D) with insulation bushing (E) and washer (F)
through the fixing irons and into the concrete floor, Page 34
• Hammer the two expander screws into position.
• Secure the two expander screws and earthquake bracing by tightening the
screws until the red caps snaps off, Page 35
Note: The red cap snaps off when the screw has been tightened to the
proper torque, exposing a green washer. The green washer should be
intact, with no breaks. If the washer is found damaged during inspection,
the screw must be verified to have a minimum torque of 64 Nm (but not
exceeding 68 Nm).
• Proceed to the next installation stage, Section 4.2.8 on page 35 .
4.2.8 Fastening the Cabinets
Fasten the cabinets to each other either side-by-side or back-to-back.
35
6/1531-ASP 113 01 Uen J2 2008-07-17