Hardware Installation
Figure 21 Securing the Earthquake Bracing
Note: The following procedure must be performed for the feet at the front
and for the feet at the back:
Place two expander screws (D) with insulation bushing (E) and washer (F)
through the fixing irons and into the concrete floor, Page 34
Hammer the two expander screws into position.
Secure the two expander screws and earthquake bracing by tightening the
screws until the red caps snaps off, Page 35
Note: The red cap snaps off when the screw has been tightened to the
proper torque, exposing a green washer. The green washer should be
intact, with no breaks. If the washer is found damaged during inspection,
the screw must be verified to have a minimum torque of 64 Nm (but not
exceeding 68 Nm).
Proceed to the next installation stage, Section 4.2.8 on page 35 .
4.2.8 Fastening the Cabinets
Fasten the cabinets to each other either side-by-side or back-to-back.
35