60 | NGC8200 AND PGC1000 USER MANUAL | 2101510MNAH
Figure 6-24: Stream Setup (Stream 1)
4. When all the desired changes have been made, click Send and then Next to move to the next
screen.
5. Complete the configuration at each screen presented and click Next. When the last screen for
the stream is completed and you click Next, the Stream Setup tab appears again for the next
stream.
6. Start configuration of the second stream on the Stream Setup tab and go through all the
screens.
7. Complete steps 1 and 4 for each additional sample stream.
8. Click Next on the last screen for the final stream. The Calibration tab displays (see section
6.5.3, next).
IMPORTANT NOTE: During the stream setup, each time Next is selected you should see the
Stream ID located on the first line of each screen. Update values as required. M
streams even if the device is a single stream device.
Table 6-5: Stream setup screens
Setup Tab Values
Stream ID Assign unique identifier (10 alphanumeric digits)
Location Enter meter location (24 alphanumeric digits)
Stream 1, Stream 2, Stream 3
Contract Pressure 14.73 PSIA (default) KPa, InH20, Mbar, InHg, PSIA,
Bar, mmHg, MPa, Pa or kgcm2
Contract Temperature 60.00 F (default) C, F, R or K