Manual Power Quality Filter PQFS Commissioning instructions 141
—
8 Commissioning instructions
8.1 What this chapter contains
This chapter presents the steps to follow to commission the active filter. The
commissioning of your PQF should be conducted in strict accordance with this
procedure.
Before applying the commissioning procedure, make sure that you are familiar with:
− The filter hardware (discussed in Chapter 4
).
− The mechanical installation requirements (discussed in Chapter 5).
− The electrical installation requirements (discussed in Chapter 6).
− The PQF programming interface PQF-Manager (discussed in Chapter 7).
− If the Modbus option has been installed, please refer to the document
“2GCS212013A0050-RS-485 Installation and Start-up guide” for more information
on this item.
The commissioning procedure consists of 9 steps that should be strictly followed.
Table 52: Steps to follow to commission the active filter
Visual and installation check
Step 2 Setting the address of each unit in a multi-unit filter and terminate the CAN
bus
Voltage rating and phase rotation check
Step 4 Basic commissioning parameters setup
Step 5 Automatic and manual CT detection procedure
Before starting the filter
Step 9 Set up the user requirements
Section 8.11 presents the commissioning report to be filled in when commissioning the
filter.