GUID-354976C3-2B17-4C71-B271-FDBDDABB61F4 V1 EN
Figure 61: RCB clients
1
RCBs configured for the IED
2 RCB clients
The clients are added or removed automatically to the corresponding
data sets in the Data Sets tab. Date sets are based on the configuration
done in the Reports Controls tab and vice-versa.
7.6 Substation section configuration in the IEC 61850
Configuration tool
The substation topology consists of the substation, voltage level and bay nodes. The
bay nodes include also the conducting (primary) equipment, which corresponds to the
switches, that is, the circuit breakers, disconnectors, and earth switch, of the
configured IED. In addition to the substation topology configuration, logical nodes of
Section 7 1MRS757809 C
Engineering of event reporting with PCM600
94 REC615 and RER615
Engineering Guide