Machine Maintenance Procedures 3-7
Disassembly Process 0
The disassembly process is divided into the following sections:
Main unit disassembly
LCD module disassembly
The flowcharts provided in the succeeding disassembly sections illustrate the entire
disassembly sequence. Observe the order of the sequence to avoid damage to any of the
hardware components. For example, when removing the mainboard, remove first the
Base Cover, the Battery, the WLAN module, and the LCD Module in that order.
Table 3-1. Main Screw List
Size Quantity Acer Part No.
SCRW M2.0X2.5-I(BZN)(NLK)(D6.0) 4 86.GG2N7.002
SCREW M2.0*3.0-I(BZN)(NYLOK) 10 86.M8NN7.001
SCREW M2.0*4.0-I (NINYLOK)
(D5.5T0.8I)
9 (Wi-Fi)
86.GM9N7.001
10 (LTE)
SCREW M2.0*6.1-I (BNI) (SW) D4.5
IRON
12 86.VA2N7.001