12 American Dryer Corp. 112144-46
Even though a 12-inch (30.48 cm) clearance is acceptable, it is recommended that the rear of the dryer be positioned
approximately 2 feet (0.61 meters) away from the nearest obstruction, i.e., wall, for ease of installation, maintenance,
and service.
The dryer must be installed with a proper exhaust duct connection to the outside.
The dryer must be installed with provisions for adequate combustion and make-up air supply.
CAUTION: This dryer produces combustible lint and must be exhausted to the outdoors. Every 6
months, inspect the exhaust ducting and remove any lint build up.
IMPORTANT: Dryer must be installed in a location/environment, which the ambient
temperature remains between 40º F (4.44º C) and 130º F (54.44º C).
C. DRYER ENCLOSURE REQUIREMENTS
Bulkheads and partitions should be made of noncombustible materials and must be located a minimum of 12-inches
(30.48 cm) above the dryer outer top, except along the front of the dryer, which may be closed in if desired.
NOTE: Even though a minimum of 12-inches (30.48 cm) above the dryer outer top is acceptable, a
clearance of 18-inches (45.72 cm) or more is suggested for ease of installation and service
(power electrical connections).
NOTE: When fire sprinkler systems are located above the dryers, a minimum of 12-inches (30.48 cm)
above the dryer outer top is required.