INSTALLATION
IEPMU01/02 POWER MOUNTING UNIT INSTALLATION
I-E96-508C 3 - 15
22. Turn PEP circuit breakers on.
NOTE:
Before doing step 23, verify that switch and jumper settings
on the power modules are correct. Refer to Section 3 for settings.
23. Install the required number (calculated from SIZING THE
MODULAR POWER SYSTEM in Appendix B) of PDS (or PDF)
modules in the PMU one at a time. Slide 1 power module along
the guides until it is seated. Turn the 2 latching screws until
they lock. Verify that the status LED turns green on each
power module. If it does not, refer to Section 5.
24. Do not install the process modules at this time. Refer to
RECOMMENDED START-UP PROCEDURES in Section 4,
Steps 5 through 8.