5.4.2 DHK/UI test procedure
! Do not check any damaged and/or severely corroded
components.
458881-29_Ko
1
2
3
4
5
Fig. 38: Block diagram of DHK/UI connection
1 DHK/UI flushing connection/test connection
2 Injection chamber
3 DHK/UI
4 Connection adapter
5 High-pressure hose
i The prerequisites to be observed when checking
and adjusting DHK/UI can be found in the test
instructions for DHK/UI in ESI[tronic]2.0. These
test instructions do not form part of the scope of
delivery. ESI[tronic] 2.0 can not be installed on the
EPS 205.
Procedure:
1. Clean the DHK/UI (see Sec.5.3).
2. Fit the injection chamber on the DHK/UI.
i A UI can only be connected using the UI connection
adapter (special accessory).
3. Attach the DHK/UI (Fig.38, item3) to the clamp
(Fig.3, item3).
! To avoid twisting and premature wear, do not
connect the high-pressure hose directly to the DHK/
UI.
4. Connect the high-pressure hose with the connection
adapter (Fig. 38, item 4, 5) to the DHK/UI.
! The connection adapter must be tightened to
a torque of between 25 Nm and 30 Nm. If the
connection between the connection adapter and the
DHK/UI is leaking, the screw connection is not to
be re-tightened. In the event of a leak, unfasten the
connection again, clean the sealing surface and re-
connect the connection adapter applying the correct
tightening torque.
5. Connect the hose 1 680 712 362 to the quick-release
coupling of the injection chamber (Fig. 38, item 2)
and to the "DHK/UI flushing connection and test
connection" (Fig. 38, item 1).
6. Close the guard.
7. Perform the test.
i DHK/UI testing is described in the Online Help.