Logamatic EMS – 6 720 801 387 (2011/05)
21
Commissioning
5
5.2 Checklist: important parameters for commissioning
When commissioning the device, ensure the satisfaction of both parties, making sure that the
heating system meets the customer's needs and will not give cause for complaints. In our
experience, the following parameters are very important for the satisfaction of the system user:
B Find out the system owner's requirements and preferences regarding:
Setting options
Standard
setting
SERVICE
MENU\
Settings\
The required type of reduction
(night setback)
Outdoor setback
mode; Reduced
operation; Room
setback mode; Shut-
down mode
Outdoor
setback
mode
Heating circuit x,
page 32
The required control mode Outside temperature
compensated, room
temperature
compensated
Outside
temperature
compen-
sated
Heating circuit x,
page 35
of the correct heating curve
By means of the
following parameters:
design temperature,
minimum outside
temperature, offset, and
set room temperature
Heating circuit x,
page 32
of the correct building type
(damping of the outside
temperature)
Light, medium, heavy Medium Plant data,
page 27
of the switching frequency of the
circulation pump.
1)
1) This function is not possible with boilers with UBA1.x, DBA, UBA-H3 or with DHW with
instantaneous water heating.
Permanent operation,
1 x, 2 x, 3 x, 4 x, 5 x, 6 x
per hour for 3 minutes
at a time
2 x DHW, page 41
DHW priority Yes, No Yes Heating circuit x,
page 33
Switching program
(times)
Standard program
(e.g. family), user
defined program
Family Heating circuit x,
page 34
Table 8 Checklist: important parameters for commissioning