ENGLISH 8 / 78 CAP. 5 - INSTALLATION
5.1.1 Unpacking MULTIGAS 8500
RISK OF OVERTURNING - CRUSHING -
BUMPING
Position the pallet on a level surface, remove the carton after eliminating the straps that bind
it. Free the equipment from the pallet by cutting the straps that block it. Remove the unit from
the base pallet of the package by using suitable means. Once on the ground, the unit is
handled on the four wheels; the two smaller wheels have brakes.
5.1.2 Scale unlocking
Under the machine there is a bolt locked by a wing nut, which locks the scale during
transport, once the equipment is delivered to the client the lock must be removed to make
the scale operational.
Stabilise the equipment with the brakes of the front wheels.
Insert hand under the equipment from the front side, unscrew the wing nut, when the bolt is
free to move, unscrew it for 4 turns and then lock it in that position by locking the wing nut.