Installation Checklist
Use the checklist in Table 4-1 when installing the Polycold Cryochiller. Perform the procedures in the
order shown. Initial and date each procedure as you complete it.
NOTE: Before installing the Polycold Cryochiller, check the specifications and site requirements in
this manual.
Table 4-1: Installation Checklist
Name Completion Page
1. Installation Overview 4-3
2. Inspect and Unpack the Polycold Cryochiller Balance
Pressure:_______
4-4
3. Move to Location 4-7
4. Remove Compressor Hold-Down Nuts 4-9
5. Connect Cooling Water 4-10
6. Connect Electrical Power 4-13
7. Install the Cryosurface 4-17
8. Install the Refrigerant Lines 4-19
9. Install the Condensate Drain Tube 4-26
10. Check the Refrigerant Lines and Cryosurface for Leaks 4-27
11. Evacuate the Refrigerant Lines and Cryosurface 4-32
12. Connect the Refrigerant Line Thermocouples 4-36
13. Preliminary Check of the Polycold Cryochiller 4-39
14. Insulate Exposed Refrigerant Tubes and Couplings 4-41
15. Startup and Test 4-46
16. Evaluate the Polycold Cryochiller / Place Into Service 4-48
17. Install Seismic Restraints (as required) 4-51