4 System shutdown
36 Installation and maintenance instructions Logano GE315 • Issue 02/2006
We reserve the right to make any changes due to technical modifications.
3.2 Making the system operational
Observe the following during commissioning:
z Prior to commissioning vent the heating system via
radiators and air vents.
z Check, whether the hot gas baffle plates have been
correctly inserted.
3.3 Commissioning the control device
Please check in the documentation of the series 4000
control device, which you are using, how to commission
the control device.
3.4 Start up the burner
z Proceed with the commissioning of the burner in
accordance with the installation and maintenance
instructions included with the burner.
z Complete the commissioning report included in the
burner documentation.
You may raise the flue gas temperature, if you discover
during measurements for the commissioning report, that
the flue gas temperature is too low for the type of
chimney used (danger of condensation).
Fig. 49 Check the location of the hot gas baffle plates

Table of Contents

Other manuals for Buderus Logano GE315

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Buderus Logano GE315 and is the answer not in the manual?

Buderus Logano GE315 Specifications

General IconGeneral
BrandBuderus
ModelLogano GE315
CategoryBoiler
LanguageEnglish

Related product manuals