78
TE-BBR Instruction and Operation Manual
2. On a lab table or bench, place two 16" high boxes or two 16" high stacks of books approximately 8"
apart.
3. Carefully lift the Load Frame out of the TE-BBR bath. While maintaining the Load Frame in its vertical
position, transfer it to the table and orient so that the Load Frame is suspended in its vertical
position on the 16" supports. Refer to Figure 34. Clean and dry the Frame.
Figure 34: Supported Load Frame
4. Using the stubby flat blade screwdriver, remove the four screws/washers securing the twin beam
supports to the base of the Load Frame. The screws are located on the underside of the Load Frame.
Refer to Figure 35.
Figure 35: Load Frame Supports
5. Set the screws/washers removed in Step 3 aside. Remove the old beam supports from the Load
Frame.