5. Installation Check-up
WATER CONNECTIONS
No leaks from the connections or tubes
FUNCTIONING
Boiler and operating pressures are normal.
The pressure gauge is working properly.
The self-leveling device is working properly.
The expansion valves are working properly
GROUPS
+RRNXSWKH¿OWHUKROGHUVWRWKHJURXSVZLWKRXWFRIIHH
Let each group dispense water for about a minute.
HOT WATER
Continuously dispense hot water (pressing the appropriate button) until at least 5 litres of water have been used
for a machine with 2 groups and 8 litres for a machine with 3 groups (see the “Hot water dispensing” chapter in the
User’s Manual).
STEAM (also with Turbosteam)
Dispense steam from the nozzles for about a minute, using the appropriate buttons.
WARNING: AFTER INSTALLATION, CHECK TO SEE IF THE MACHINE IS WORKING PROPERLY (see the
Installation Module C).
WARNING: ONCE THE MACHINE HAS BEEN INSTALLED AND IS READY FOR USE, BEFORE ALLOWING
THE WORKER TO START USING THE MACHINE, WASH THE INTERNAL COMPONENTS ACCORDING
TO THE INSTRUCTIONS BELOW: