Model CFC ClearFire Commercial Boilers
32 Rev. 05-2012
Figure B5-25. Condensate Treatment Tank for Multiple Boilers
Gas Fuel
Connections
The local Gas Company should be consulted for the requirements for installation
and inspection of gas supply piping. Installation of gas supply piping and venting
must be in accordance with all applicable engineering guidelines and regulatory
codes. All connections made to the boiler must be arranged so that all components
are accessible for inspection, cleaning, and maintenance.
A drip leg should be installed in the supply line before the connection to the boiler.
The drip leg should be at least as large as the gas piping connection on the boiler.
See Figure B5-25, and Figure B5-26 for piping suggestions.
To Drain
Condensate Drain Trap
1" NPT Minimum Header Size
(Use PVC Pipe or other Nonferrous Material)
Neutralization Tank
12” Minimum
Neutralization Media
Cond. tank can be
mounted under boiler