Casing Assembly Model FLE Assembly
3-14 750-192
Figure 3-24. Finishing the Wetpack Insulation
Installation
Figure 3-25. Packing the Top of the Walls
Figure 3-26. Filling the Joint with Silicone Caulking
5. Finishing the Wetpack Installation
Around the Lower Drum
Unfold the wetpack to cover the lower drum and
tubes. Cover the entire base drum, overlapping
adjoining wetpack rolls. Continue to mold the wet-
pack around the lower drum and tube sections to
prevent the plates from coming apart while packing
the insulation (Figure 3-24).
The wetpack should be positioned to be level with, or
just outside the base refractory at the front.
6. Finish Installing Backing Plates
As in step 3, install the front upper and lower back-
ing plates.
7. Install Front Wall Section
To install the front wall section, repeat the same
steps used to install the rear wall. In a hot water
unit, the front wall will be one piece and the instal-
lation will be much easier, but the front wall of a
steam boiler will have two pieces just like the rear.
8. Install Roof Panel
Tidy the top of the walls to get them ready for the
roof (pack the insulation, wipe off the wall, etc) (Fig-
ure 3-25).
Fill any joints in the top of the front and rear walls
with silicone caulking (Figure 3-26).
Using spray adhesive, place a strip of 1/4” paper
gasket along the width of the front and rear walls
(Figure 3-27). Using the same process, place a small
square of the material on the 4 inside corners of the
walls, allowing a little metal to show through (Figure
3-28).